- Waiting on RFI response
- Re-work
- Submittal Turnaround
- Procurement
- Hurricane Prep
- Waiting on Permit
- Material Delivery
| Field | Description |
|---|---|
| Status | |
| Expected Date | early finish; user-generated |
| Deadline | late finish; calculated |
| Priority |
Status
Identified Priority = Successor’s priorityIn progress Priority = Successors Latest Start - Issue Expected Date - 1d Deadline = Expected Finish Successors Early Start -1d = Early Finish
Successors Late Start -1d = Late Finish WE need an early, expected, and late.? Can be start or finish Late dates come from successor ==Actual Start = Date created== If has a predecessor, generate early & late start from blocker, expected start from canvas.