Start
When the task’s status is not set tostarted, finished, or completed, the value start will be set to the target start date (or early start date if not in a valid dependency path). Otherwise, it will be set to the actual start date.
Finish
When the task’s status is not set tofinished or completed, the value finish will be set to the target finish date (or early finish date if not in a valid dependency path). Otherwise, it will be set to the actual finish date.