The problem with Gantt charts
Gantt charts are long task lists. Without the left half of the Gantt chart, known as the bar chart, this task list would be useless. Gantt charts are not glanceable. With an average of 75-100 activities per tabloid-sized page and 2,000 activities per $100M of construction value, you’re left with hundreds of pages of task list. Do you want to know when you need to install lockers on the 3rd-floor spa? You’ll need several minutes of page turning to find your dates. Want to know what’s blocking you and how much wiggle room you have in your start and finish dates? You can try all day, but you’ll never find the answer to this. Do your dates seem a bit off? Are you curious what the scheduler has blocking you? Too bad, the schedule provides hard dates, start and finish only, with no indication of how flexible or important your activities are.What if designs were communicated like Gantt charts?
Construction documents typically include sets of sheets for each discipline, for each floor, for each elevation, with no shortage of cut sheets, details, and cross sections. This means the structural column on the first floor will appear in multiple drawings: the first floor plan for all disciplines, any enlarged floor plans, the column schedule, the foundation plan, and possibly a few details. It’s important to note that you may find specific information about the column in certain locations and other information in different places. In some instances, the column serves primarily as context for other elements in the design. The design documents are communicated in many dimensions, primarily x, y, and z, with additional information layered on top. If designers provided designs like we provided schedules using Gantt charts, then we would get something like the following:- Sometimes we would get designs broken up by discipline, sometimes not.
- The architect would design the Structure, MEP, finishes, etc., with no input from consultants.
- Like milestones, Grid lines would move with every revision.
- One grid line wouldn’t move until the very end of the project, and it would be an as-built.
- There would be no details on how different building elements interface with each other.
- Huge areas like the pool would be completely missing.
- Enlarged floor plans would be issued just weeks before they were worked on.
- Instead of a mechanical room design, we would just get a label that says
Mechanical Room. - There would be one drawing only for the entire design.
- The design would be redesigned every two weeks.
- Nothing would be clouded.
- The project would be about 30% larger than originally planned
What if schedules were communicated like designs?
- We would have a plan for each trade or group of trades, with other trades shown for context.
- We would have ‘section cuts’ for critical areas, like an “Electrical Rooms” plan.
- There would be key plans included in the schedule.
- The same task would show up on multiple pages to show dependencies.
- Sheets would have different axes; the x-axis represents time, but the y-axis can represent labor, area, or work quantity, etc.
- Sheets would be color-coded according to trade or other metadata.
- Views would be provided to show the quantity of work and productivity for different tasks.
- We would have fewer pages and less paper to print on.